Trans Mountain Oil Pipeline Risks Delays If Route Change Isn't Approved

Trans Mountain Oil Pipeline Risks Delays If Route Change Isn't Approved

OilPrice.com

Published

Trans Mountain Corporation (TMC) warned this week in a filing to the Canada Energy Regulator that the oil pipeline expansion project could be delayed by several months and incur additional costs if the regulator doesn’t approve a last-minute change in a small section of the route.  The company has asked the regulator to approve a change from its approved route on a 1.3-kilometer (0.8 mile) section south of Kamloops, British Columbia, Reuters reports. The current construction method of micro-tunneling through the section is not technically…